ERCOT 4CP: 2025 peak dates, the formula and who pays

4CP stands for four coincident peaks: the 15-minute intervals when demand on the ERCOT grid peaked in June, July, August and September. A Texas business site that has reached 700 kW at Oncor, or more than 700 kVA at CenterPoint, pays its transmission charge on its own average demand in those four intervals. The four readings from one summer set that charge for the whole of the following year.

By Wire & Watt Published Updated

What 4CP means.

ERCOT, which runs most of the Texas grid, records the single 15-minute interval with the highest system demand in each of June, July, August and September. Those are the four coincident peaks. The Public Utility Commission of Texas uses them to share out transmission costs: each transmission owner’s approved cost is divided by the average ERCOT demand in the four intervals, and each delivery utility pays its share on its own demand at those moments (Substantive Rule 25.192(b)(1) and (d)).

Oncor and CenterPoint pass that cost to customers through a line called the transmission cost recovery factor, or TCRF. For most business sites the TCRF is charged on the month’s own peak. For the largest sites it is charged on their 4CP demand instead, so what the site drew in four quarter-hours of the previous summer decides a year of transmission charges.

How your 4CP is calculated.

Both utilities use the same definition: the average of the site’s integrated 15-minute demands at the time of each month’s ERCOT system 15-minute peak, for June, July, August and September of the previous calendar year. Oncor measures it in kW, CenterPoint in kVA.

4CP = (June + July + August + September demand at ERCOT’s peak) ÷ 4

An example at Oncor. A site drew 950 kW at the June peak, 1,040 kW in July, 1,010 kW in August and 1,000 kW in September. The 4CP for this site is 4,000 ÷ 4 = 1,000 kW. At the TCRF rate in effect from October 4, 2026, its transmission charge is 1,000 × $6.536625 = $6,536.63 a month. Over 12 months at an unchanged rate that is $78,439.50, though the rate itself changes every March and September.

The site’s own peak for the month does not enter this charge. A site that runs at 1,400 kW on a cool morning in May but drew 1,000 kW at the moments of ERCOT’s peaks pays transmission on 1,000. Its other delivery charges are still priced on its own peak; our guide to demand charges covers those.

Who is billed on 4CP.

Each utility sets the threshold in its own tariff, and the two utilities word it differently:

4CP billing for secondary service, from each utility’s tariff and Rider TCRF
OncorCenterPoint
Billed on 4CP fromAn NCP demand of at least 700 kW in any previous billing monthAn NCP demand greater than 700 kVA in any previous billing month, whatever the meter
TCRF on 4CP$6.536625 per 4CP kW (Oct. 4, 2026)$6.177655 per 4CP kVA (Sept. 1, 2026)
TCRF for other sites over 10 kW$4.606104 per NCP kW, on the month's own peak$4.342591 per NCP kVA, on the month's own peak
New 4CP figure applies fromJanuary 1, fixed for the calendar yearThe February billing month, fixed for a year

NCP demand is the site’s own highest 15-minute demand in the billing month. Once a site has crossed the line in any month, it moves to 4CP billing. A site with no summer history yet, such as a new building, is billed on its monthly NCP demand at the NCP rate until it has one. CenterPoint labels the 4CP group “IDR” in its TCRF table, but its tariff applies the 700 kVA test whatever meter the site has.

A smaller site with demand charges pays the TCRF on its own monthly peak. That rate is lower per kW, but it moves with every month’s peak rather than four readings a year. Our Oncor and CenterPoint guides list every delivery charge for both groups.

When the new figure applies.

ERCOT must file each year’s 4CP results with the Commission by December 1, and the rule says they are “used to bill transmission service for the next year” (25.192(d)). The utilities’ tariffs set the retail dates:

  • Oncor: the customer’s average 4CP demand is updated on January 1 and stays fixed for the calendar year.
  • CenterPoint: it is updated with the February billing month and stays fixed for a year.

So the summer of 2025 set 2026’s 4CP charges, and the summer of 2026 will set 2027’s. The rate per kW is a separate matter: the Commission’s rule has utilities update the TCRF every March 1 and September 1 (25.193(b)(1)), and Oncor’s tariff also shows revisions effective August 1 and October 4, 2026. A firm figure always needs its effective date.

The 2025 and 2026 peaks.

ERCOT reported the 2025 4CP dates on December 1, 2025. We could not open ERCOT’s own file on the day we checked, so the dates below are as published by trade press reporting that filing; three outlets agree on them.

ERCOT 4CP days, 2025 (set 4CP charges for 2026)
MonthPeak day
JuneThursday, June 19, 2025
JulyWednesday, July 30, 2025
AugustMonday, August 18, 2025
SeptemberThursday, September 4, 2025

All four were weekdays. The official 2026 intervals are due from ERCOT by December 1, 2026; until then, any 2026 date in circulation is an estimate. We will add them when ERCOT publishes.

The 12CP proposal.

On July 24, 2026 the Texas Register published a proposal from the Public Utility Commission of Texas to replace the 4CP method with a 12CP method: one 30-minute ERCOT peak in each of the 12 months from October through September, averaged. The proposal is Project 58000, written to carry out Section 6 of Senate Bill 6 from the 89th Legislature. The proposal would also have transmission owners remove 4CP wording from their tariffs within 30 days of adoption.

As of November 2, 2026 we found no adopted rule: the Texas Register’s adopted rules up to October 30, 2026 do not include it, and the rule text still describes 4CP. Until a rule is adopted and the tariffs change, 4CP billing stands. If 12CP is adopted, a site’s transmission charge would depend on its demand at 12 peaks a year instead of four, which changes what reducing summer peaks is worth.

How to lower it.

Only the site’s demand at the four peak moments counts, so the lever is cutting load at those moments, not cutting the month’s peak. At Oncor’s October 4, 2026 rate, a site whose 4CP comes down by 100 kW pays $653.66 less a month in transmission, or $7,843.95 over a year at an unchanged rate. The same 100 kVA at CenterPoint is $617.77 a month.

ERCOT’s peaks fall on hot summer weekdays, but which day and which quarter-hour is only known afterwards, which is why sites that manage 4CP reduce load on the days a peak looks likely. Some suppliers send warnings for this: NRG, for example, says its program “provides alerts in the morning on potential coincidental peak days.” Ask your supplier whether it offers 4CP alerts. Our load factor calculator shows how steady the site’s use is, and our quote comparison checklist covers how supply offers treat transmission charges. Start with your business ZIP and email, and add every page of a recent bill for each site.

Common questions

What does 4CP stand for?
Four coincident peaks: the four 15-minute intervals when the ERCOT system's demand peaked in June, July, August and September. The Public Utility Commission of Texas divides each transmission owner's costs by the average demand in those four intervals (Substantive Rule 25.192(b)(1)).
How is 4CP calculated for a business?
Take the site's own 15-minute demand at the moment of each month's ERCOT peak, June to September of the previous calendar year, and average the four. Oncor and CenterPoint both define it that way in their tariffs.
Who pays 4CP charges in Texas?
At Oncor, any site that has reached an NCP demand of at least 700 kW in a previous billing month. At CenterPoint, any site that has exceeded 700 kVA in a previous billing month, whatever kind of meter it has. Smaller demand-billed sites pay transmission on their own monthly peak instead.
How much is the 4CP charge?
At Oncor, $6.536625 per kW of 4CP demand each month from October 4, 2026; at CenterPoint, $6.177655 per kVA from September 1, 2026, for secondary service. A site with a 1,000 kW 4CP at Oncor pays $6,536.63 a month at that rate. The rates are updated every March 1 and September 1.
When do 4CP charges change?
Two things change. The site's 4CP demand is recalculated once a year: from January 1 at Oncor and from the February billing month at CenterPoint. The rate per kW (the TCRF) is updated each March 1 and September 1 under Substantive Rule 25.193.
When were the 2025 4CP peaks?
June 19, July 30, August 18 and September 4, 2025, as ERCOT reported on December 1, 2025. The 2025 peaks set 4CP transmission charges for 2026. All four fell on weekdays.
How do I know when a 4CP peak is coming?
Not for certain: which day and which 15 minutes were the peak is only known afterwards. Sites that manage 4CP cut load on hot summer weekday afternoons when a peak looks likely, and some suppliers send alerts on those days. NRG, for example, sends morning alerts on potential peak days.
Is ERCOT replacing 4CP with 12CP?
12CP has been proposed, not adopted. In July 2026 the Public Utility Commission of Texas proposed measuring transmission costs on 12 monthly 30-minute peaks from October to September (Project 58000, under Senate Bill 6). As of November 2, 2026 no adoption has been published, so 4CP still applies.

Sources and scope

Supplier explanations support the general contract and billing points in this guide. Your own agreement and service location determine the terms that apply to you.

Wire & Watt wrote this guide from the sources below. No supplier or utility paid for it or reviewed it. The supplier a business chooses pays us, never the business: how we’re paid.

Put it into practice

Have a contract to review?

Start with your business ZIP, business name and email. Add every page of your bill when you have it. With Box Energy, we compare available offers. No fee for our help.

Start my rate comparison

Before you choose

Make sense of your next contract.

Contract timing

Business electricity contract renewal: when it ends

What happens when a Texas business electricity contract ends: the 14-day notice and no-penalty rules for small accounts, and how early to lock the next term.

Read the guide
Quote comparison

How to compare commercial electricity quotes

Line up business electricity quotes on the same basis: same meter, usage, start date and term, what each rate includes, and what to check before you sign.

Read the guide
Bill basics

How to read a commercial electricity bill (Texas)

Usage, supply, delivery, demand and taxes: what each line on a business electric bill means, which one a new contract changes, and what to have ready.

Read the guide
Demand charges

Demand charges: what they are and how to lower them

Why a business pays for its busiest 15 minutes of the month, how demand differs from usage, what a ratchet and 4CP do, and how to lower the peak. Texas rules.

Read the guide
Delivery charges

Oncor TDU delivery charges for businesses (2026)

What each Oncor delivery charge pays for, why 2026 business bills changed (new rates June 1, a surcharge from August, riders October 4) and the 80% ratchet.

Read the guide
Calculator

Oncor demand ratchet calculator

Work out the demand Oncor bills a Texas business this month: the 80% ratchet, its 20 kW and 25% load factor exemptions, and your load factor band.

Read the guide
Delivery charges

CenterPoint TDU delivery charges for businesses (2026)

What each CenterPoint delivery charge on a Houston business bill pays for, why it's billed in kVA, the 2026 rider changes, and how it differs from Oncor.

Read the guide
Prices and charges

Texas commercial electricity prices and delivery charges

What Texas businesses pay for electricity on average (EIA, monthly) and the current Oncor and CenterPoint business delivery charges, dated to each tariff.

Read the guide
Rate types

Fixed vs variable business electricity rates in Texas

What each rate type lets a Texas supplier change, why sites under 50 kW can only buy fixed or variable, and what to ask about an indexed plan.

Read the guide
Load factor

Electricity load factor: how to calculate it, and what's good

Load factor compares a business's average electricity demand with its peak. Calculate it from three numbers on your bill, see what counts as good, and how to raise it. Calculator.

Read the guide
Bill basics

ESI ID: what it is and how a Texas business finds it

The ESI ID identifies each electricity service point in Texas: what it looks like (17 or 22 digits), where it is on the bill, and how to look it up.

Read the guide
Demand

Power factor charges in Texas: the 95% rule

Power factor is kW divided by kVA. Below 95%, Oncor, AEP Texas and TNMP can raise billed demand, and CenterPoint bills in kVA. The rule, an example, the fix.

Read the guide
Delivery charges

TDU delivery charges in Texas: what businesses pay

What TDU delivery charges are, which Texas utility serves your site, every AEP Texas and TNMP business charge, and a calculator that checks a month's bill.

Read the guide
Data

Oncor vs CenterPoint vs AEP vs TNMP delivery charges

What the same business pays each month for delivery from Oncor, CenterPoint, AEP Texas and TNMP, at three site sizes, from current tariffs. Download the CSV.

Read the guide
Basics

Commercial electricity: what it is, how it's billed and what businesses pay

What makes electricity "commercial", how a business bill differs from a home one, whether it costs less per kWh, and what a restaurant, hotel or store pays a month, from EIA data for August 2026.

Read the guide
Data

Commercial electricity prices by state, per kWh (August 2026)

What businesses pay for electricity in every state and DC: EIA's commercial average per kWh for August 2026, the change in a year and since 2020, and industrial and residential for comparison. Download the CSV.

Read the guide
Restaurant electricity

Put your restaurant’s rate beside the options.

Start with your business ZIP. Add your bill now or later. We compare available supply offers with Box Energy.

Start my comparison